The old railway bridge at Newbridge has been removed as part of plans to transform the railway line between Ebbw Vale and Newport.
The bridge has been removed to accommodate a second track at Newbridge Road over Bridge Street which will be widened.
From Saturday, October 22 the Ebbw Vale railway line has been closed to replace and install the new railway bridge at Newbridge and extend the platform at Llanhilleth and Newbridge stations.
The line will reopen on October 31 – during this time Transport for Wales (TfW) will provide a replacement bus service between Ebbw Vale Town and Cardiff Central.
Nicky Stephenson said: “We hope the new bridge will have a positive impact on the town.
“It is part of the local history, it’s the end of an era.”
Work will be done in a series of blockades, Network Rail released when the Ebbw Vale line will be shut.
Planned Ebbw Vale line closures:
22nd-30th October
18th-19th march
25th-26th march
27th may – 11th June
The extensive work is to introduce a new hourly service between Ebbw Vale Town and Newport, two miles of new track will be laid between Aberbeeg and Crosskeys to create a seven-mile passing loop.
Nick Millington, interim route director at Network Rail Wales & Borders, said: “It’s fantastic to see the transformation of the Ebbw Vale line really take shape.
"This multi-million-pound investment will transform services on the line and really benefit the communities it serves.”
The works are funded by Blaenau Gwent Council who received a loan from the Welsh Government to allow the second service, completion is set for late next year.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel